Installation Guidelines for Vehicle Lifts

I. Pre-Installation Foundation Requirements
To prevent equipment tilting, abnormal noise, or collapse due to weak foundations, ensure the following before installation:
Newly poured concrete must cure for at least 20 days.
Requirements vary by lift capacity:
≤4.5-ton two-post lifts:
Concrete strength: C25
Thickness: ≥200mm
5–6-ton two-post lifts:
Concrete strength: C30
Thickness: ≥250mm
8-ton two-post lifts:
Concrete strength: C30–C35
Thickness: ≥400mm
Horizontal error between two posts: <5mm.
Ensure lift baseplates directly contact the concrete foundation for stability.
II. Workspace Dimensions
Recommended bay size: (7000–8000) x 4000mm (4S standard).
Ensure sufficient space for vehicles to drive onto/off the lift.
Prevent vehicles from hitting ceilings. For low ceilings, install ceiling proximity alarms.
III. Power & Air Supply Setup
Electrical requirements:
Three-phase wire: ≥2.5mm²
Single-phase wire: ≥4mm²
Power outlets must be installed 1.5m above ground near the main post.
For temporary power during installation: Provide 415V three-phase power.
Ceiling height:
4m for overhead lifts.
3.5m for baseplate lifts.
IV. Tools & Materials Preparation
Per two-post lift:
13L of L-HM46 anti-wear hydraulic oil.
2T+ forklift for unloading and moving equipment.
Follow the manufacturer’s detailed installation tool list.
V. Erecting Posts & Aligning Dimensions
For overhead lifts: Pre-assemble crossbeams on the ground.
Route hoses, wires, and cables through crossbeams to both posts.
For baseplate lifts: Erect posts directly and confirm dimensions.
Maintain ≥3m clearance between walls and lift baseplates.
Adjust post spacing per lift model specifications.
VI. Securing Expansion Bolts & Adjusting Post Verticality
Use drill bits matching bolt sizes.
Drill holes 3cm deeper than bolt length.
Clean debris, insert bolts, and secure.
Use a plumb bob to ensure posts are vertical, then tighten bolts.
VII. Installing Pump Station, Wiring, & Lift Arms
Mount the pump station on the post.
Fix the control box to the post.
Connect limit switches, motor cables, and wiring to the control box.
Fill the pump reservoir with No. 46 anti-wear hydraulic oil.
Install lift arms with shorter arms toward the vehicle front.
VIII. Power Connection & Lift Testing
Connect the control box to external power.
Raise the lift 400mm (vent inverted cylinders by loosening air-release valves; upright cylinders require no venting).
Lower the lift fully and tighten cables.
Verify synchronous operation of safety locks on both posts.
Test with a vehicle: Raise to maximum height, engage locks, and ensure 3cm clearance at the upper limit.
IX. Commissioning & Operation
Apply grease to lift cables and slide rails.
Tighten all hose fittings and bolts.
Train operators on safety protocols before use.
For assistance, contact office during business hours or local distributors.
Commentaires